Work completed between July 16th - August 12th, 2010
- Sandstone patio
- Installation of long awaited sliding glass doors with flush triple track system
- Tiled basement & extension kitchens, bathrooms & utility rooms
- Laid, sanded & varnished parquet floors
- Painted basement bedroom, lvg space, bathroom, utility room & kitchen
- Painted mezzanine level bay window bedroom (not pictured)
*************************
We're almost done!! 13 days to completion!!!!!!!!
*************************
Newly plastered walls AND screed flooring completed
(skylight above this alcove area)
under arch to the left is the doorway into the den area of extension
Basement: alcove area to right and this room is a bedroom space
Basement: looking from bedroom into
open-plan kitchen/living space
Basement: lvg space/open-plan kitchen
(utility room to right)
Antonio removed the old institutional-looking
Well area - Black sandstone coping stones to be
laid by Antonio on top of well walls
To be rendered & painted white on Aug. 17th
Full view of patio from inside extension before sliding doors
are installed (kitchen space to right)
External view looking in to kitchen space (left) from patio
(I love my flush floor level with patio!)
orange waste pipe (it's the 2010 "in" colour for plumbing
pipes :) the den is in the background (right)
Looking forward to August 25th, 2010!!!!!!!!